NEWS OF FLINDERS PIER WORK
In summary, the documents include several detailed assessments. The document entitled RFI Response says that the replacement of some piles will be subject to budget. The document states that: “Depending on the available funding, Parks Victoria may need to prioritise pile replacement and omit certain packages (of works) from the scope of works.” In other words, there may be insufficient funding from the Government to complete the works properly and replace all 54 piles that need replacing. This caveat should be a concern to all 45,000 Victorians who joined the campaign to Save Flinders Pier.
The advertised permit to commence repair works is now open for public comment.
Public consultation for the planned repair works to the Flinders Pier closes next Tuesday (11 March). If you wish to make a submission, here is a link: https://www.heritage.vic.gov.au/…/currently…/_nocache